Old Maasarm:
To allow the Old Maasarm to flow again, a number of dykes will be removed and high spots will be additionally deepened or excavated and the bottle neck near the Brugstraat in Wanssum will also be lifted.
High-water channels:
To realise high-water channels, 1.8 million m3 of soil will be excavated at Ooijen (on an area of some 120 football pitches, an average of between 1 and 3 m will be excavated). In Wanssum, between 0 and 2 m will be excavated on an area of some 170 football pitches.
To complete the project, Infranea provided support in working out the As-Built drawings. The main part of the work consisted of processing the measurements for Hoogwatergeul Ooijen, Hoogwatergeul Wanssum and Dijkring Broekhuizenvorst into a 3D model. The 3D model was then represented in longitudinal profiles and an overview drawing.
In addition, the landscaping elements and the green-blue structure were represented in separate AB drawings. Finally, support was provided to complete the final peripheral drawing work.
Start: November 2017
End: March 2021
Combination Mooder Maas (Dura Vermeer – Ploegam)
Eu 31.012,50
Michel Dekker